Independent public-interest researchEvidence verified through August 10, 2026
Anchor investigation · CC-001

Pacifico Cedar Creek

A proposed 710 MW natural-gas generation facility at 382 Earl Callahan Road, evaluated here as both a standalone JETI applicant and part of an emerging data-center and energy corridor.

Site-suitability conclusion

This project should seek another location

The conclusion is about this site—not a claim that no large power project could ever be built responsibly. A 710 MW plant requires an industrial setting with adequate buffers, emergency capacity, water, access, and a complete permitting record.

Community exposure854 homes within 1 mile

Privacy-safe county data show 2,247 anonymous residential sites within two miles and 5,701 within three. Fifteen schools or childcare locations also sit within three miles of the filed perimeter.

Hazard and responseDrought and wildfire are present facts

The site is in D2 Severe Drought as of July 21, 2026, in a region shaped by the 2011 Bastrop Complex and 2015 Hidden Pines fires. Industrial-fire capability remains unverified.

Scale and cumulative load710 MW cannot be treated as a small local use

The filing pairs the plant with roughly 490 MW of IT load while Amazon and multiple EdgeConneX-related campuses are assembling along the same corridor.

What a more suitable site would demonstrate before approval

  • Substantial separation from homes, schools, and childcare.
  • Verified fire-water, apparatus, staffing, mutual aid, and evacuation capacity for the full buildout.
  • A sustainable water source tested against drought and cumulative demand.
  • Full major-source and aggregation analysis for every turbine, generator, and related operation.
  • Road, pipeline, transmission, noise, lighting, and drainage infrastructure suited to continuous industrial use.
See the surrounding community
The public-money loop

Why Cedar Creek—and why Texas?

Texas is investing in BlackChamber. Cedar Creek is asking Texas for help. TMRS committed $150 million to two BlackChamber funds. BlackChamber appears on the Cedar Creek construction record. Pacifico says tax incentives materially affect the Texas project. No public record proves that TMRS money finances Cedar Creek—but Texas is already on both sides of the deal.

See the loop
VerifiedTexas public money$150M committed to BlackChamber funds
UnknownProject financingThe Cedar Creek money trail is not public
VerifiedCedar CreekBlackChamber named on the 304-acre construction record
Requested supportTexas is asked to help againTax relief · county abatements · water service
The horror in one sentence: Texans may help capitalize the developer, lower the project’s costs, supply its water, and live with its consequences—while the tenant remains secret.
New records · August 9

A formal TCEQ challenge is pending—and both authorizations remain active

Two amended motions ask TCEQ to review and stay Pacifico's and Black Chamber's construction-stormwater authorizations. TCEQ has not stayed or overturned either record, and the motions' allegations are not agency findings.

Read the August 9 record sweep
Likely data-center developerTXR1551YV

Black Chamber Partners

BCG Cedar Creek Campus · 304 acres

Black Chamber is the construction-stormwater operator for the data-center-named footprint and publicly describes its business as digital-infrastructure development. The hyperscale customer or tenant remains undisclosed.

Power-side operatorTXR1565YW

Pacifico CCK Energy 1

B&W Ranch · 173.54 acres

A dedicated Pacifico entity holds construction-stormwater coverage for the generation footprint. It registered in Texas one day before the reported county grading and abatement filings.

Official verification

Use TCEQ's search

TCEQ's internal detail pages are not durable public permalinks and can return “page does not exist” when opened from a shared link, so copy and paste the Program ID numbers instead.

Open TCEQ Central Registry
  1. Open Central Registry (CR) Query.
  2. Choose Program ID Search.
  3. Enter either authorization number below.
Black Chamber PartnersTXR1551YV
Pacifico CCK Energy 1TXR1565YW
Shared regulated siteRN102987831
Planned initial disturbance477.54 acresDisturbed land—not building footprint
Estimated mobilizationSeptember 2026Filed estimates—not evidence of a start
Water-service outcomeTabled Aug. 4Second tabling; no return date confirmed
Publicly traceable air permitNot yet foundTCEQ pending list checked August 9
Important distinction

Active stormwater coverage is not approval of the project.

These authorizations cover construction-related stormwater discharges under a statewide general permit. They do not authorize the turbines, air emissions, buildings, grading plans, groundwater production, wastewater, roads, pipeline work, or the overall data center. Each operator had to prepare a detailed SWP3 with site maps, but those drawings are not attached to the public permit summaries.

Read the governing permit
Developer due diligence

Separate Pacifico projects clarify what Cedar Creek still needs

These are not evidence of Cedar Creek impacts or outcomes. They are clearly labeled comparisons that identify records and decision questions local reviewers should require here.

Primary TCEQ comparisonSeparate Pecos County project

GW Ranch has a full public air record

35 simple-cycle turbines in the TCEQ summary

Pacifico's separate GW Ranch record names turbine groups, operating assumptions, controls, startup and shutdown allowances, and pollutant-specific emissions. That is the level of project-specific disclosure still missing for Cedar Creek.

Independent record reviewSeparate Hood County project

Fort Spunky turned on water-source certainty

Concept plan revoked; litigation pending when reported

The Texas Tribune reports that Hood County revoked the separate Pacifico-affiliated project's concept plan after its proposed utility water source fell through. Pacifico sued the county. That does not decide Cedar Creek, but it makes a definitive water source and clear local authority essential before approval.

Read the public-record investigation
Project timeline

The filings are advancing on parallel tracks

Corporate formation, water engineering, county applications, school-tax incentives, and construction-stormwater coverage have moved in a coordinated sequence. Labels distinguish completed public-record events from future dates that remain estimates.

  1. Government relations

    Pacifico retains a Texas lobbyist

    Texas Ethics Commission disclosures identify Pacifico Energy as a client of Austin lobbyist Jay P. Brown beginning in 2025 and continuing in 2026.

  2. Ohio alternative

    No application filed before the moratorium

    Muhlenberg Township minutes say Pacifico requested blank zoning and variance forms but submitted nothing. Three weeks later, trustees imposed a one-year data-center moratorium.

  3. Corporate structure

    Pacifico Cedar Creek Holdco registers

    A new Texas holding company appears. Its exact ownership and financing role are not disclosed in the public account-status record.

  4. Water

    Aqua tables large-volume service

    Aqua WSC’s board does not approve Pacifico’s request. Staff requires a revised feasibility study after identifying the development as a data center.

  5. Corporate and county filings

    Power operator forms; grading and abatements follow

    Pacifico CCK Energy 1 registers on June 17. Local reporting says the county received two grading applications and two tax-abatement applications the next day.

  6. School-tax incentive

    Pacifico signs JETI application J0049

    The filing seeks a school-tax limitation for the power facility and describes the adjacent computing load, pending permits, economics, and competing-site claim.

  7. Construction stormwater

    Black Chamber coverage becomes active

    TXR1551YV identifies Black Chamber Partners as operator for the 304-acre BCG Cedar Creek Campus. An approved Notice of Change follows the next day; its changed fields are not public.

  8. JETI supplement

    Pacifico formally separates the JETI scope

    Supplement 1 limits qualified investment to the power facility and describes the data center as unrelated and third-party-owned, while retaining the generation-and-load relationship.

  9. Construction stormwater

    Pacifico power-side coverage becomes active

    TXR1565YW identifies Pacifico CCK Energy 1 as operator for 173.54 acres of planned disturbance at the same B&W Ranch regulated site.

  10. Stormwater procedure

    Two amended motions ask TCEQ to review and stay both authorizations

    TCEQ indexes the Motions to Overturn under Pacifico's TXR1565YW. They also seek review of Black Chamber's TXR1551YV. Both authorizations remain active; no stay or Commission order is posted, and the filings' assertions are not agency findings.

  11. County policy

    Signed countywide abatement policy adopted

    The official signed record confirms adoption for a two-year term and marks Commissioner Mark Meuth absent. This made the County eligible to consider abatements; it did not approve Pacifico's individual applications.

  12. Water-service decision

    Aqua places possible approval on its agenda

    Official Agenda Item 13 schedules discussion and action on approving large-volume service through Resolution No. 26.08.02. The posted agenda does not attach the revised feasibility study or resolution.

  13. Water-service outcome

    Aqua tables the request a second time

    Aqua confirms that its Board voted to table Item 13 / Resolution 26.08.02. The posted packet is marked DRAFT and TABLED, its signature lines are blank, and no return date is confirmed.

  14. Next public action

    Countywide industrial-authority resolution

    Commissioners Court will consider Item E.4, asking state leaders for stronger county power over large industrial development. It is relevant to data centers but does not name or decide Pacifico.

  15. Filed estimate—not a start notice

    Both operators estimate construction mobilization

    Black Chamber lists September 1 and Pacifico September 30. These are estimated dates in stormwater filings, not proof that grading or construction has begun.

Why there is a Supplement 1

Separated for JETI. Still connected in the filing.

Pacifico first filed JETI application J0049 in June 2026. It then filed a dated July 16 follow-up—Supplement 1—within the same application record to revise and clarify material being evaluated by the Comptroller, including project scope, maps, excluded existing improvements, the competing-site narrative, and the economic-benefit model. It is not a separate project or a replacement for the original filing; both must be read together.

Verified filing content

The JETI project is generation only

Pacifico now says its qualified project consists solely of the natural-gas generation facility. It excludes all data-center assets, buildings, operations, investment, and property.

Supplement 1, page 3
Applicant statement

The data center is described as unrelated

Pacifico says a third party would own, finance, develop, and operate the adjacent data center, with no Pacifico ownership or operational control.

Supplement 1, page 3
Independent comparison

The scale relationship remains

The filing still pairs approximately 710 MW of generation with approximately 490 MW of IT load and anticipates a data-center operator as primary off-taker for part of the output.

Trace this finding →
Methane-fired generation at community scale

The technology is industrial. The surrounding land use is residential.

Natural gas is composed primarily of methane. Pacifico proposes a 710 MW facility using multiple simple-cycle combustion turbines, fast-start peaking turbines, fuel-gas compressors, air-cooled equipment, transformers, switchgear, tanks and emissions controls. That equipment creates siting questions that cannot be answered by calling natural gas “clean” or by considering each permit in isolation.

Air pollution and health

Combustion controls reduce pollution; they do not eliminate it.

EPA identifies nitrogen oxides and carbon monoxide as primary gas-turbine pollutants, with volatile organic compounds, hazardous air pollutants and particulate matter also possible. Nitrogen oxides and VOCs also help form ground-level ozone. EPA associates elevated NO₂ with airway irritation and worsened asthma, particle pollution with heart and lung effects, and ozone with airway inflammation and asthma attacks. With homes, schools and childcare close to the filed perimeter, the public needs the actual emissions inventory, operating hours, stack data and dispersion modeling—not technology labels.

Continuous and low-frequency noise

A daytime sound check cannot represent an around-the-clock plant.

Turbine inlets and exhausts, compressors, cooling fans, transformers and other rotating equipment create broadband, tonal and low-frequency sound. DOE materials specifically flag high levels of low-frequency noise as a gas-turbine concern in data-center energy systems. If the plant follows a constant hyperscale computing load, nearby receptors could experience persistent nighttime operation; Pacifico’s actual duty cycle remains unfiled. A receptor-by-receptor study must cover normal operation, starts, shutdowns and emergencies.

Fire, explosion and incident response

The hazard is larger than a flame at the turbine.

The proposed system adds high-volume methane delivery and compression, hot turbine enclosures and exhausts, lubricating oils, transformers, switchgear and other ignition or fuel sources. NFPA maintains a dedicated power-plant fire-protection standard for hazards of this kind. In severe drought and a wildfire-affected landscape, approval should require a project-specific hazard analysis, leak detection, fixed suppression, fire-water calculations, apparatus access, evacuation analysis and verified local mutual-aid capability.

Waste heat and localized temperature

Simple-cycle generation rejects a large amount of heat.

In a simple-cycle turbine, high-temperature exhaust is not routed through a steam bottoming cycle to make additional electricity. EPA says turbine exhaust remains several hundred degrees, and EIA reports simple-cycle systems use substantially more fuel per unit of electricity than combined-cycle plants. Pacifico also lists air-cooled fin-fan equipment and Organic Rankine Cycle units, but their final configuration is unknown. This does not prove a particular off-site temperature increase; it does require quantified heat-rejection, exhaust-plume and summer microclimate analysis before siting the plant beside an existing community.

Operating duration and cumulative burden

“Peaking” equipment does not answer how the full campus will run.

Pacifico describes dedicated, reliable generation supporting approximately 490 MW of IT load, plus fast-start peaking turbines. That makes the missing hourly operating profile critical: residents need to know which units can run, for how long, how often they start, what happens during grid or equipment failures, and how the plant combines with backup generators and other corridor sources. Health, noise, heat and emergency impacts must be modeled cumulatively for the maximum reasonably foreseeable buildout.

Animated optical gas imaging footage showing hot exhaust plumes above a row of gas turbines
Animated OGI reference footage · xAI Memphis · Oilfield Witness
Aerial photograph of six gas turbine packages at Brotman Generating Station in Texas
288 MW Brotman Generating Station · ProEnergy
Visual evidence

The exhaust is mostly invisible. The industrial footprint is not.

Aqua's open-record production now includes a May conceptual campus plan, but no final rendering or turbine equipment schedule. Comparable facilities and thermal footage cannot tell us exactly what will be built; they help show the likely industrial scale, repeating stacks, turbine enclosures, hot exhaust and support equipment that the concept sheet leaves abstract.

Every image is labeled as a real facility, source footage, developer rendering, or AI-generated illustration.

See the complete visual record
Project record

What is filed—and what each number means

Applicant figures are reported as applicant figures. Filing status is not operational status.

Applicant
Pacifico Cedar Creek LLC
Filed site
382 Earl Callahan Road, Cedar Creek, Texas
Generation
710 MW site-rated redundant power
Associated IT load
Approximately 490 MW
Investment
$2.237 billion in the revised consultant model
Permanent jobs
25 applicant-projected positions
Starting payroll
About $3.5M, down from about $6.2M
Property
Narrative says ~2,842 acres; listed parcels total ~2,810
Construction operators
Black Chamber Partners · 304 acres; Pacifico CCK Energy 1 · 173.54 acres
Water service
Aqua tabled the request again August 4; the study models 23 LUEs and a 14-gpm peak with no fire flow, contingent on major capital improvements
Modeled tax relief
Approximately $143.7M on the power side over ten years, subject to final agreements and eligibility
Pipeline screening
Four mapped transmission corridors cross the listed parcels; exact easements and fuel connection remain unverified
Risk record

Why this location requires a higher evidentiary bar

Each card distinguishes a verified regional condition from a missing project-specific showing.

Wildfire and emergency response

The regional fire history and ESD 1's adopted fire code are verified. The project-specific plan review, fire-water system, apparatus access, industrial-response capability, staffing, and evacuation consequences are not yet public.

Air emissions

The applicant identifies turbines and emissions controls, but the exact unit inventory, stacks, operating hours, emissions limits, and dispersion modeling remain unavailable.

Water supply

Aqua’s revised study models only 23 LUEs, a 14-gpm peak, and no fire flow. It does not establish total campus demand, cooling water, annual volume, fire-water supply, the final source mix, or drought terms; the proposed resolution nevertheless says Aqua has capacity to serve a data center.

Noise and lighting

No project-specific public noise study or final layout establishes continuous, startup, shutdown, tonal, or low-frequency impacts at nearby receptors.

Traffic, access, and evacuation

County and TxDOT access approvals were listed as pending. Construction traffic, heavy-haul routes, emergency access, and shared evacuation bottlenecks require cumulative review.

Drainage and land disturbance

Active stormwater coverage identifies 477.54 acres of planned disturbance. Two amended motions now ask TCEQ to review and stay both authorizations, but neither is suspended and the motions' allegations are not agency findings. The required SWP3 maps and county grading and drainage files remain unavailable.

Public finance

The power-side filing appears to seek roughly $143.7 million in ten-year tax relief, while its comparative financial proof remains confidential and its named Ohio alternative was not formally filed before a local moratorium.

Cumulative industrialization

Black Chamber now appears in the public record as construction operator for a 304-acre data-center footprint beside Pacifico’s 173.54-acre power footprint. Power, water, roads, pipelines, and emergency response cannot be assessed in isolation.

Statewide precedent—not a Pacifico allegation

Review the full buildout before local approvals make it a fait accompli.

The Texas Tribune and Floodlight documented Texas projects that first obtained minor air authorizations and later pursued much larger turbine or generator fleets. EPA guidance warns that permit restrictions or project segmentation that do not reflect the planned operation can circumvent major-source preconstruction review.

There is no public evidence in this record that Pacifico has already used that tactic. The lesson is procedural: the county should require one full-buildout account of every turbine, generator, stack, operating scenario, affiliated facility, and co-located load before tax abatements, grading, or other discretionary approvals move ahead.

JETI decision standard

The public claim is not the statutory finding

Pacifico has stated that incentives matter. The Comptroller must still determine that the agreement is a compelling factor and that the investment would not occur in Texas without it.

Current law

§403.609(b)(3) remains in force

The failed SB 2322 proposal cannot be used as though it created an exemption for dispatchable generation.

Read the statute
Public subsidy scale

The power-side model implies about $143.7M in relief

This independent estimate combines modeled county and ESD abatements with estimated JETI school-tax relief. It is not an approved award and excludes the data-center-side application.

Check the applicant tax model
Named alternative

Ohio had no filed zoning application

Township minutes say Pacifico requested blank forms but filed nothing before the one-year data-center moratorium.

Read the township record
Research agenda

Nine questions that can change the case

These are not rhetorical questions. Each names the next record needed.

CriticalTurbines

Manufacturer, model, unit count, ratings, and duty cycle?

Next evidence: TCEQ equipment inventory and NSR application

CriticalAir

Stack heights, locations, exit conditions, annual hours, and modeled receptors?

Next evidence: TCEQ application and dispersion-modeling files

CriticalWater

Aqua WSC service, groundwater wells, or a hybrid supply—and what annual demand?

Next evidence: All-source water balance, cooling design, fire-water plan, CIP schedule and completion evidence, final NSSA, fees, and groundwater-district records

CriticalFire

Fire-water storage, pump redundancy, hydrants, apparatus access, and suppression design?

Next evidence: County and fire-jurisdiction plan review

HighSite

Why does the sum of listed parcel acreage differ from the narrative site acreage?

Next evidence: Parcel records, survey exhibits, and boundary GIS

CriticalOwnership

Who is the hyperscale customer, and what affiliate, financing, control, site-development, or exclusivity relationships connect it to Black Chamber and Pacifico?

Next evidence: Owner-agent forms, site-control instruments, contracts, utility studies, financing records, and tenant disclosures

CriticalOfftake

Is there a signed PPA, capacity agreement, term sheet, letter of intent, exclusivity agreement, or reservation?

Next evidence: Non-confidential agreement descriptions and records requests

CriticalJETI

What specific competing-site evidence is confidential, and does any currently actionable alternative exist?

Next evidence: Land, permitting, utility, corporate, and Comptroller records

HighEconomics

Why did starting permanent payroll fall roughly 44% while headcount remained 25?

Next evidence: Underlying wage, occupation, benefits, and escalation assumptions

Primary record

Start with the records

The dossier is a reading layer over the sources—not a substitute for the applications, permits, minutes, and official status reports.

DOC-0001 · June 2026Applicant filing in government record

JETI Application J0049

Original application describing the energy and data-center relationship, project boundary, equipment, permitting status, and modeled economic benefits.

Open source
DOC-0008 · July 16, 2026Applicant filing in government record

Pacifico Cedar Creek JETI Application Supplement 1

Narrows the JETI project to the gas-generation facility, expands the compelling-factor narrative, identifies the paused Ohio alternative, maps excluded existing improvements, and revises the economic model.

Open source
DOC-0015 · July 14–18, 2026Primary government database

TCEQ Authorizations TXR1551YV and TXR1565YW

TCEQ records show active construction-stormwater coverage for Black Chamber Partners’ 304-acre BCG Cedar Creek Campus footprint and Pacifico CCK Energy 1’s 173.54-acre power-side footprint at the same regulated site. At the linked Central Registry page, open the CR Query, choose Program ID Search, and enter TXR1551YV or TXR1565YW.

Open source
DOC-0017 · June 3, 2026Primary utility record

Aqua WSC June 3 Board Minutes

Approved minutes show the board tabled Pacifico Energy Development’s large-volume Zone 2 water-service request after staff identified the development as a data center and required a revised feasibility study.

Open source
DOC-0022 · January 12, 2026Primary local-government record

Muhlenberg Township January Proceedings

Minutes state that Pacifico requested blank zoning-change and variance forms, had not submitted applications, and did not attend the meeting after being invited.

Open source
DOC-0023 · February 2, 2026Primary local-government record

Muhlenberg Township February Proceedings

Minutes record adoption of a one-year data-center moratorium following substantial public opposition, making the named Ohio alternative paused and less advanced than the Bastrop site.

Open source
DOC-0024 · Checked August 9, 2026Primary government status report

TCEQ Pending New Source Review Applications

The updated pending list still contains no publicly identifiable NSR entry under the known Pacifico, Black Chamber, B&W Ranch, CCK, Earl Callahan, or Cedar Creek project identifiers. This does not prove that no pre-application work exists.

Open source
DOC-0038 · Indexed August 2026Primary agency docket

TCEQ Commissioners’ Action Item 147527 / Docket 2026-0805-WQ

TCEQ indexes a procedural challenge under Pacifico authorization TXR1565YW. Two amended motions received July 20 ask the Commission to review and stay both TXR1565YW and Black Chamber authorization TXR1551YV. The authorizations remain active; no stay or Commission order is posted.

Open source
DOC-0040 · Effective October 1, 2023Primary emergency-services record

Bastrop County ESD No. 1 Fire Code and Local Amendments

ESD 1 adopted the 2018 International Fire Code and local provisions governing plan review, permits, inspections, fire flow, hydrant distribution, fire-department access, private fire mains, pumps and tanks. Aqua's 'Fire Flow: None' does not establish project compliance with these separate requirements.

Open source