Immediate action

Call Gerdes and Schwertner now—before TCEQ acts

TCEQ logged the supervisory-review milestone on September 2. Call Rep. Stan Gerdes at 512-321-3720 and Sen. Charles Schwertner at 512-463-0105 today. Ask both offices to contact TCEQ leadership immediately, urge no approval until the corrected record and written PSD/ORC analysis are public, press for a voluntary public meeting, and publish every agency response. Use the call and email scripts below.

The central question

Has Pacifico demonstrated that this expedited permit track fits the complete project?

Does the current public record actually demonstrate that Pacifico Cedar Creek qualifies for the expedited Electric Generating Unit Standard Permit, or do unresolved project-scope, emissions, and PSD classification issues require correction—or case-by-case review—before TCEQ acts?
01

Does the application reconcile with itself?

No.

Several internal arithmetic, schedule, and summary issues remain in the released filing.

02

Does it reconcile with the rest of the record?

No.

Other government filings describe different equipment, entities, and project relationships.

03

Were conflicting descriptions publicly reconciled?

No public reconciliation located.

Material descriptions overlapped across agency records without an identified explanation.

04

Does the plan satisfy this permit track?

Unresolved.

The missing ORC and enforceability questions could affect the governing PSD threshold.

The public record

At a glance

Air registration185019 · Project 413471 · RN102987831
Proposed air-permit configuration48 simple-cycle gas turbines
Stated maximum nominal output1,326 MW
Pacifico’s reported NOx233.61 tons per year
NOx after PGM70 displayed-value adjustmentApproximately 240.26 tons per year
Operating-permit statementThe application identifies the site as Title V-major; no separate Title V project was located
TCEQ status checked September 2Pending; “final package to team leader or supervisor” milestone logged
Second deficiency cycleOpened September 1; closed September 2—one elapsed calendar day
Corrected final package publicly locatedNo
Only have two minutes?

The short version

  • The released application does not reconcile itself. Its PGM70 schedule lists 11 turbines, but the NOx subtotal equals six times the displayed per-unit value. Applying that value to all 11 raises the independent result from 233.61 to approximately 240.26 tons per year.
  • Its SMT60 schedule shows 8,760 normal hours in one table and 4,380 normal hours plus startup and shutdown in another. Combining the higher schedule with the PGM70 adjustment yields an approximately 249-ton diagnostic scenario. That is not an official potential-to-emit calculation and remains below 250 tons.
  • Other government records describe an ORC, a co-located data center, behind-the-meter generation, and interconnection equipment in ways the turbine-only air filing does not reconcile. Those divergences do not by themselves prove aggregation, circumvention, or improper motive.
  • The missing ORC matters because TCEQ staff raised the possibility that the earlier heat-recovery configuration could fall within a named PSD category using a 100-ton-per-year threshold, rather than the general 250-ton threshold Pacifico relies on.
  • TCEQ’s second deficiency cycle lasted only September 1–2. TCEQ then logged a final-package supervisory-review milestone, but no deficiency notice, response, corrected application, final technical review, or signed authorization is publicly available. All controlling status fields remain PENDING.
Read this precisely

What the evidence does—and does not—establish

  • The confirmed inconsistencies do not prove that emissions exceed 250 tons per year or that Pacifico is ineligible.
  • The missing ORC does not prove permanent abandonment, improper motive, segmentation, or an intent to restore it later.
  • The altered EPA quotation does not decide PSD eligibility or identify who edited the filing.
  • Project size alone does not make Pacifico ineligible; a source can be Title V-major yet PSD-minor if the 250-ton threshold properly applies.
  • The one-day deficiency cycle does not reveal what TCEQ raised, what Pacifico changed, or why the cycle closed so quickly.
Question 1 · The application itself

Does it reconcile with itself? No.

Pacifico’s site-wide summary reports 233.61 tons per year of nitrogen oxides, or NOx. The PGM70 schedule lists 11 turbines and displays a per-unit NOx value of 1.33 tons per year, but its group subtotal is 7.98 tons—exactly six times the displayed per-unit value.

Applying the displayed values to all 11 listed PGM70 turbines, while leaving the rest of Pacifico’s calculation unchanged, produces the following independent adjustment. Because the displayed per-unit values are rounded, these are diagnostic—not definitive corrected totals.

PollutantPacifico’s totalDisplayed-value adjustment
CO200.22 tpy208.67 tpy
NOx233.61 tpy240.26 tpy
PM, PM10, and PM2.5207.83 tpy214.53 tpy
SO₂51.66 tpy53.01 tpy
VOC108.14 tpy113.24 tpy

A second schedule conflict narrows the claimed margin

One table assigns the SMT60 group 8,760 normal operating hours; the detailed calculation uses 4,380 normal hours plus startup and shutdown. Combining the higher schedule with the PGM70 adjustment produces approximately 249.02 tons per year of NOx. That screen assumes the 8,760-hour entry is operative rather than a table error; it is not an agency determination and still remains just below 250 tons.

Other unreconciled items

  • The unit worksheets appear to total approximately 12.33 tons per year of sulfuric-acid mist, but that pollutant is absent from the site-wide summary.
  • The worksheets say their operating scenarios “shall not be used to limit” actual hours, startup and shutdown events, or natural-gas firing.
  • The released filing does not assemble a clear source-wide annual cap, averaging period, monitoring method, calculation procedure, recordkeeping system, and reporting mechanism for the public to test.
Generating capacity appears at three levels of precision

Section 5’s coarse schedule states 1,326 MW. Re-adding the rounded model values in Appendix A’s Unit Specific Emissions Summary produces 1,325.76 MW, which rounds to 1,326. But multiplying the more precise power outputs in the six detailed model Table 1s by their unit counts produces 1,328.674 MW. The difference may reflect different rating or reference conditions rather than an equipment change; the application should identify which capacity definition governs and reconcile the three presentations.

Question 2 · The wider government record

Does the application reconcile with the rest of the record? No.

The project appears under different affiliated Pacifico entities and materially different descriptions depending on the filing. The record identifies affiliated Pacifico special-purpose entities under shared governance; it does not establish that Pacifico controls Black Chamber, the data-center operator. TCEQ—not this review—must determine any legal aggregation, stationary-source, or support-facility consequence.

Cross-record table 01Entity and role map

This map separates the Pacifico affiliates from the separate same-site link to Black Chamber. Different entity names alone are not evidence of wrongdoing, but TCEQ should identify the complete applicant, owner, operator, source, and support-facility boundary.

Filing or venueNamed entity or personRole presentedRelevant overlap or limit
Air Registration 185019 Pacifico CCK Energy 1 LLCRegistrant and owner-operatorThe application’s Section 9 names Pacifico Cedar Creek LLC as the “source”; the Core Data Form was certified by a vice president of another affiliate, Pacifico Energy Development LLC.
Aqua water record Pacifico Energy Development LLC; Nayanika Panickar as developer contactApplicant for service described as serving a data centerThe same Pacifico affiliate group appears in the data-center water request and generation filings.
JETI J0049 Pacifico Cedar Creek LLCTax-incentive applicantLists ORC units and interconnection equipment as qualified property; the public air filing uses a different affiliate.
Bastrop County plan setsCedar Creek Power Plant and BCG Cedar Creek CampusPower-plant and campus development recordsA combined drainage report addresses the campus and power plant; this is evidence of coordinated site development, not by itself a PSD aggregation finding.
Texas corporate-management recordsFour Pacifico special-purpose entitiesAffiliated project companiesRecords reviewed by Lost Pines Watch list the same governing person, registered agent, and principal address for the Pacifico entities. This does not establish control of Black Chamber.
Cross-record table 02When the project is—and is not—presented as a data-center development

These descriptions are facially difficult to reconcile. They do not themselves decide common control or federal source aggregation.

RecordHow the project is describedRelationship presentedEvidentiary limit
JETI project description Behind-the-meter generation designed to serve a co-located hyperscale data-center campus; an integrated energy and digital-infrastructure hub.IntegratedAn applicant description to the Comptroller, not an air-agency aggregation decision.
TCEQ RN102987831 Power-generation codes and a data-processing code appear on the same regulated-entity record; Black Chamber and Pacifico CCK Energy 1 attach as operators/owner-operator.Same RNA regulated-entity record does not by itself decide the stationary-source boundary or common control.
County drainage record“BCG Cedar Creek Campus & Cedar Creek Power Plant” addressed in one engineering report.Coordinated siteShared civil engineering does not alone establish PSD aggregation.
Aqua request A Pacifico affiliate sought water service described as serving a data center.Coordinated requestThe request does not establish Pacifico’s control of the data-center operator.
JETI Supplement 1 Describes the data center as separate from and unrelated to the applicant’s project and excludes it from the tax project’s scope and costs.SeparateThe same supplement retains the power-supply relationship; the statement was made by Pacifico Cedar Creek LLC, while the air registrant is an affiliate.
Air registration Analyzes the turbine-generation facility; the data center’s 24/7 load is not stated as an enforceable operating constraint.Functionally separateAbsence from this filing is not, by itself, a legal source-boundary determination.
Cross-record table 03How core project features appear across agencies
FeatureAir · TCEQWater · AquaTax · JETICounty plans
ORC / heat recoveryAbsent; simple-cycle turbines onlyPresent on the June study exhibit“ORC units” listed as qualified property“ORC SYSTEM (TYP.)” on July 13 and 17 sheets
Project relationshipGeneration facility analyzed on its ownService request described as serving a data centerBehind-the-meter generation for a co-located hyperscale data center; supplement also calls data center separate and unrelatedCampus and power plant addressed together in a drainage report
Grid equipmentNo complete intended grid configuration identified in the released applicationNot addressedOn-site substation, switchyard, and BBEC interconnection equipment listedNot resolved by the cited plan records
Named Pacifico entityPacifico CCK Energy 1 LLCPacifico Energy Development LLCPacifico Cedar Creek LLCCedar Creek Power Plant / campus names

“Behind the meter” does not mean “off grid.” Interconnection hardware also does not prove import or export capability. The defensible point is narrower: the public record does not reconcile the intended grid configuration.

Aqua studied a water configuration tied to an older plant description

Aqua’s operative feasibility study evaluated a developer-supplied domestic profile of 23 living-unit equivalents, 9 gallons per minute maximum-day demand, and 14 gallons per minute peak-hour demand. The exhibit in that same packet still depicts industrial plant elements, including an ORC, chiller yards, turbines, and gas-turbine-wash and fire tanks. Aqua’s June 3 minutes say the earlier request was tabled after the developer “has been identified as a data center” and would need a revised feasibility study. The public record does not contain a later study reconciling the subsequent project changes.

Question 3 · Overlapping descriptions

Did conflicting descriptions sit in government records without a public reconciliation? Yes.

The relevant point is chronology, not accusation. The public record shows materially different descriptions overlapping while agencies evaluated the project; it does not establish which person made any change, that a filing was intentionally misleading, or that Pacifico plans to restore omitted equipment.

Unreconciled itemWhere it appearedSupported chronology
JETI “ORC units” vs. turbine-only air applicationComptroller JETI record and TCEQ Air Registration 185019The filings coexisted from the August 14 air submission until Pacifico’s reported August 19 JETI withdrawal. An official Comptroller disposition remains unconfirmed.
Altered EPA quotationWhite paper submitted on Pacifico’s behalfThe added words appear in the clean filing submitted by August 7, but not in the August 4 original or August 5 redline.
ORC-bearing water and county records vs. ORC-free air filingAqua June study, July county plans, and August air applicationThe public records retain both descriptions; no abandonment statement or cross-agency reconciliation was located.
PGM70, SMT60, and sulfuric-acid-mist issuesReleased air application and TCEQ project logThe issues remain in the released application. TCEQ recorded deficiency cycles August 21–26 and September 1–2, but the notices are not public, so the record does not show whether TCEQ raised these points.
Source-accuracy recordWhat happened here? The altered EPA quotation

During the ORC classification dispute, a revised white paper was submitted to TCEQ on Pacifico’s behalf through Trinity Consultants. It cited EPA’s April 2022 publication, Waste Heat to Power Systems, while arguing that the ORC should not place the facility in the lower 100-ton named-source category.

The clean white paper submitted August 7 presented an EPA sentence as a direct quotation—but added words that are not in EPA’s sentence.

RecordWords presented inside the sentence
EPA, April 2022, page 3 “…using waste heat to generate steam…”
Accompanying redline, page 3 “…using waste heat to generate steam…”
Clean revision, page 3 “…using waste heat in combustion exhaust to generate steam…”

The additional words are “in combustion exhaust.” They remain inside the quotation marks, unbracketed and unmarked. They do not appear in EPA’s sentence or in the accompanying redline.

Why the added words mattered

The clean filing made EPA appear to connect that sentence specifically to combustion-exhaust heat, supporting Pacifico’s argument that its proposed system was unfired heat recovery rather than a fossil-fuel-fired steam-electric plant. EPA discusses combustion exhaust elsewhere in the publication, but those words are not part of the quoted sentence.

The insertion supported Pacifico’s advocacy; it does not decide PSD eligibility. The released record does not identify the editor or establish intent. The precise conclusion is that the altered quote appeared in a filing submitted on Pacifico’s behalf through Trinity Consultants—not that any identified employee, consultant, or lawyer made the change.

Question 4 · The authorization path

Does the project fit the permit track TCEQ is reviewing? The public record does not resolve it.

Earlier project records included an Organic Rankine Cycle, or ORC, that would recover gas-turbine exhaust heat through thermal-oil and cyclopentane equipment to generate additional electricity. Released correspondence shows TCEQ staff raised the possibility that the configuration could be treated as a fossil-fuel-fired steam-electric plant—a named PSD category potentially subject to a 100-ton-per-year threshold when the regulatory heat-input qualification is met.

Pacifico disputed that view. On August 11, TCEQ advised that the proposed legal path had not cleared and referred the question to its Office of Legal Services. Three days later, the submitted application described only simple-cycle turbines. It contains no ORC, Rankine or bottoming cycle, cyclopentane system, thermal-oil loop, HRSG, or comparable exhaust-energy-recovery equipment—and no statement that the earlier ORC had been permanently abandoned.

  • If the ORC was permanently abandoned, applying the general 250-ton threshold to the represented simple-cycle project has a legally plausible basis.
  • If the ORC was deferred or remains part of an integrated project, the 100-ton classification and complete-project scope questions could return.
  • If excluded heat-recovery equipment is proposed later, TCEQ should require a new written, source-wide preconstruction and PSD applicability determination before construction.
EnforceabilityWhy a source-wide operating envelope matters

Potential to emit does not automatically mean assuming every turbine runs at maximum output for 8,760 hours per year. A source can sometimes limit its potential through enforceable annual caps rather than fixed hour limits. But projected utilization is not enough by itself.

Under Texas’s Standard Permit rules , maximum-emission representations may become binding. The public still needs a complete, practical method for determining continuing source-wide compliance.

  • A source-wide limit for every regulated pollutant and a stated averaging period.
  • A calculation method covering every combination of the 48 turbines.
  • Treatment of startup, shutdown, control-system outages, and unusual conditions.
  • Monitoring, missing-data, first-year, recordkeeping, reporting, and certification requirements.
  • Safeguards that operate before a cap is exceeded—not merely afterward.
Comparator—not a prescriptionHow another large simple-cycle project made its sub-250 limits enforceable

TCEQ’s technical review for the 920-MW Shawnee Energy Center describes four 230-MW simple-cycle turbines with SCR and oxidation catalysts. The four-turbine group accepted annual caps of 248 tons each for NOx and CO, with compliance demonstrated by continuous emissions monitoring over a rolling 12-month period. Its final maximum-emissions table remains below 250 tons after the listed ancillary emissions are added.

That is a useful enforceability comparator, not a claim that Cedar Creek must copy Shawnee or install CEMS. It shows one concrete architecture TCEQ has used for a large simple-cycle project, while Cedar Creek’s released filing does not identify a comparably assembled source-wide limit and compliance system.

Read TCEQ’s Shawnee technical review · Read the signed final action and emissions table

Material update · September 2

The second deficiency cycle closed after one day; TCEQ logged a supervisory-review milestone

TCEQ’s live Project 413471 report now records three September 2 changes: the second Deficiency Cycle closed; the Final Package Rework Cycle closed; and a new milestone, “FINAL PACKAGE TO TEAM LEADER OR SUPERVISOR FOR REVIEW (DATE),” was entered. The project, permit, and action all remain PENDING. No completion date is shown for that supervisory-review milestone, and no signed authorization is displayed.

First Deficiency CycleClosed August 26
Final Package Rework CycleClosed September 2
Second Deficiency CycleClosed September 2 · one elapsed day
Final package to team leader or supervisorNo completion date
How did a second deficiency cycle open and close after only one elapsed calendar day?

The public cannot evaluate the sequence because TCEQ has not posted a deficiency letter, timestamps, Pacifico’s response, a corrected application, an emissions workbook, a change log, or the final technical review. The tracking labels do not reveal what TCEQ raised, what changed, or whether the issue was minor or significant.

The new Permit Search Portal now identifies “B & W Ranch,” Registration 185019, applicant Pacifico CCK Energy 1 LLC, as a “New Application” with “Issued: Not Applicable.” It lists zero application-history entries and zero application documents. TCEQ says newer applications are transitioning to this portal, so the earlier absence from the frozen posting list is no longer probative. Read TCEQ’s transition notice.

No underlying filing or new ORC record located

Records Online still returns zero items for Primary ID 185019, and the Title V search returns zero projects for RN102987831. We found no new filing mentioning or depicting an ORC, Rankine or bottoming cycle, cyclopentane, thermal oil, HRSG, or comparable exhaust-energy recovery. Those absences do not prove permanent abandonment, decide PSD applicability, or eliminate future Title V obligations.

Participation entries have been reclassified

As checked at 9:11 a.m. CDT on September 2, TCEQ’s Central Registry classifies 3 submissions as hearing requests, 183 as public-meeting requests, 139 as written comments, and 1 as “To Be Determined.” These are intake categories—not granted proceedings or proof that a formal meeting or hearing right exists, and TCEQ is actively reclassifying the intake. The record still shows no agency action, filing, public-meeting entry, TCEQ docket, or SOAH docket.

Verify the status through TCEQ’s Status of Air Permits and search Project 413471. Verify documents in Records Online , the operating-permit result through the Title V search , and participation classifications in the Central Registry item .

Parallel September 1 decision

Aqua approved Pacifico’s water-service item; the NSSA comes next

The following recap comes from a resident who attended Aqua Water Supply Corporation’s September 1 Board meeting. Aqua has posted the agenda, but says the September minutes will remain pending until the October Board meeting. Until Aqua publishes its official record, the meeting account, vote details, presentation contents, and speaker statements below remain attendee-reported.

The short version

  • The Board first approved Item 5, authorizing a letter supporting Lost Pines Groundwater Conservation District’s opposition to high-volume data-center water use.
  • Ten residents then challenged the continued use of Aqua’s June Pacifico feasibility study, comparing it with later JETI and TCEQ records and asking for a delay.
  • LPGCD General Manager Elvis Hernandez said Pacifico’s stated request was not large and identified larger-volume exports toward San Antonio as the district’s greater concern.
  • Pacifico developer Nayanika Panickar was called during public comment and passed without speaking.
  • Garver, Aqua’s engineering consultant, gave an approximately 18-minute presentation about the June study. Attendees say it included a site-plan image not found in the feasibility study Aqua had released; the image appeared to show one data-center building and raised a potentially material record question when compared with other public plans reviewed by Lost Pines Watch.
  • General Manager Dacy Cameron said Pacifico had confirmed that full-buildout demand remained 23 LUEs despite project changes and that Aqua could provide that amount.
  • The Board then approved Item 6, Resolution 26.09.01, over two no votes, according to attendees, with no substantive Board discussion before the vote. Many attendees stood and left, some audibly expressing disappointment.
What is—and is not—officially available

Aqua’s meeting page currently links the September agenda and says the minutes will be posted after approval in October. Lost Pines Watch has not located the signed resolution, official tally, recording, Garver slide deck, or the newly displayed site-plan image.

Meeting play-by-playOpen the detailed attendee recap

Item 5: Support for LPGCD’s water position

After a short explanation from Cameron, the Board approved a measure authorizing Aqua to send a letter supporting LPGCD’s resolution opposing data-center developments that use high volumes of water.

Item 6: Residents ask for a current study

Ten residents spoke. Their comments addressed the timing of the June feasibility study; later JETI and TCEQ project descriptions; the omitted ORC and cyclopentane equipment; floodplain issues; fire-flow changes; Aqua’s tariff language; and whether the study reflects the fully built-out, occupied development. Multiple speakers stressed that they were asking for an updated record and a 30-day pause—not a categorical denial of service.

Hernandez told the Board that Pacifico’s request was comparatively small and that LPGCD’s larger concern involved high-volume water movement toward San Antonio. Panickar was called as a public-comment speaker but declined to speak.

Garver presents; Cameron recommends approval

Attendees report that Garver representatives spoke for approximately 18 minutes, rapidly reviewing demand and infrastructure details from the June study. Their presentation displayed a site-plan image that attendees had not seen in Aqua’s released feasibility study. It appeared to depict only one data-center building and differed from other public Pacifico plans.

Cameron said Pacifico had followed Aqua’s process, had previously asked to table an earlier study because the LUE count was too high, and had confirmed that the changed project’s full-buildout demand was still 23 LUEs. She said she shared community concerns but believed Aqua had the requested capacity.

The vote and immediate aftermath

Board President David Glass moved the item to a vote without substantive Board discussion. Item 6 passed over two no votes, according to attendees. A large group then left the room, with some attendees audibly expressing disappointment.

Outside, residents spoke briefly with Panickar and another Pacifico representative. Some participants came away with the impression that an unnamed “end user” was driving schedule pressure. The exchange did not identify that party, and the public record reviewed here does not establish the customer’s identity, contractual role, or instructions.

A possible Open Meetings Act concern was raised—not resolved

An attendee re-entered to ask for roughly 30 seconds to raise whether the lengthy Garver presentation had been adequately described on the posted agenda. Aqua’s counsel declined the additional floor time and later disputed the concern in a one-on-one conversation, relying on Item 6’s authorization to discuss Pacifico. This account documents that a process question was raised; it does not establish that Aqua violated the Texas Open Meetings Act.

What happens next

The feasibility-study vote was not an executed water contract or the start of service. The consequential terms—demand, flow or LUE limits, capacity, infrastructure, costs, easements, deadlines, and safeguards—now move into negotiation of the Non-Standard Service Agreement, or NSSA.

Attendees say they understood Glass to promise continued communication and Cameron to say she would negotiate guardrails, with the completed agreement expected to return to the Board for a vote. Because the signed resolution remains unavailable, those reported commitments require written confirmation in Aqua’s official record and continued public follow-up. Residents should demand the signed resolution and Garver presentation now; publication of all written material supporting the 23-LUE “full buildout” representation and every non-privileged NSSA draft and redline; meaningful notice before any Board vote; and the final executed agreement. The reported presentation and Aqua’s tariff and Developer Guide also warrant records-based review, but this account does not itself establish a legal or tariff violation. The two no votes matter: Aqua did not act unanimously, and the water dispute now moves from feasibility to the terms of the binding agreement.

Before TCEQ acts

Six things the agency should resolve

  1. 01

    Publish both deficiency notices, Pacifico’s complete responses, every reworked or revised application and emissions workbook, the final technical review, and a change log identifying each correction.

  2. 02

    Reconcile the 11-unit PGM70 schedule and six-unit-equivalent subtotals, the SMT60 operating schedules, the sulfuric-acid-mist summary, and TCEQ’s final source-wide totals.

  3. 03

    Identify every enforceable source-wide annual limit, averaging period, and monitoring, calculation, recordkeeping, reporting, and certification method.

  4. 04

    State whether the ORC was permanently abandoned. If excluded, expressly identify every ORC, Rankine or bottoming cycle, cyclopentane system, thermal-oil loop, HRSG, or comparable heat-recovery system not authorized.

  5. 05

    Issue a written, source-wide PSD applicability determination identifying whether the 100- or 250-ton threshold applies and why the complete project qualifies for the EGU Standard Permit.

  6. 06

    Reconcile the source boundary, Pacifico affiliate roles, data-center relationship, grid configuration, auxiliary equipment, and support facilities—and require case-by-case authorization if the complete project does not qualify for this track.

Residents do not need to prove that Pacifico is already over a PSD threshold to justify these requests. The applicant and agency must produce a coherent, public, and enforceable record showing what is being authorized and why it qualifies.

Act today—not after approval

Call Gerdes and Schwertner right now

TCEQ has logged the “final package to team leader or supervisor” milestone. No public decision deadline is posted, but that is a reason to act faster, not slower. Rep. Gerdes and Sen. Schwertner represent Bastrop County. They do not decide the permit, and their requests do not guarantee a meeting; they can use constituent, oversight, and political pressure immediately—before staff signs anything.

Call now. Then send this in writing today.

TCEQ closed Pacifico Cedar Creek’s second deficiency cycle after only one elapsed day and moved Air Registration 185019 / Project 413471 at the final-package supervisory-review milestone without publishing the deficiency letter, Pacifico’s response, the corrected application, the emissions workbook, or the final technical review.

I am asking your office to act immediately—today. Please personally contact TCEQ’s Executive Director and Air Permits Division and urge them not to approve this registration until the complete corrected record is public, the internal emissions inconsistencies are reconciled, TCEQ issues a written source-wide PSD determination, and the agency explains whether the earlier Organic Rankine Cycle was abandoned, deferred, or omitted.

Please press TCEQ to hold a voluntary public meeting, demand same-day notice of any decision, and make your inquiry and every agency response public. Please tell constituents within 48 hours what action your office took. A referral or general assurance that the application is “under review” is not enough.

Put the technical request directly in TCEQ’s record

Call this a pre-decision technical submission and request for agency action, rather than a formal public comment. This EGU Standard Permit registration does not ordinarily provide the same site-specific notice, comment, meeting, and contested-case hearing process as a case-by-case NSR or PSD permit.

Subject
URGENT: Registration 185019 / Project 413471 — hold action and release final package

Before taking any final action on Air Registration 185019 / Project 413471, please publish the September 1–2 deficiency communication, Pacifico’s complete response, the corrected application and emissions workbook, every revised process description and plot plan, and the final technical review.

Please also:

  • Reconcile the 11-unit PGM70 schedule with the subtotals corresponding to six units and identify TCEQ’s final source-wide emission totals.
  • Resolve the SMT60 8,760-hour versus 4,380-hour operating-schedule inconsistency and the sulfuric-acid-mist summary issue.
  • Identify every enforceable source-wide annual limit and its monitoring, calculation, recordkeeping, reporting, and certification method.
  • State whether the ORC was permanently abandoned and expressly identify every heat-recovery system excluded from this registration.
  • Provide TCEQ’s written determination of the applicable PSD threshold and the complete project’s eligibility for the EGU Standard Permit.

Please associate this submission with Registration 185019, Project 413471, and RN102987831; route it to the assigned reviewer, team leader or supervisor, and Executive Director; confirm receipt; and provide same-day notice of any approval, denial, or other final action.

Submit the same text through TCEQ’s Comment on Pending Permits system if it accepts Registration 185019, save the confirmation, and still send the email. Do not label it as a hearing request: the intake database may classify requests, but this Standard Permit route does not create a contested-case-hearing right.

Keep the broader pressure on

After contacting Gerdes and Schwertner, ask Sens. Ted Cruz and John Cornyn to seek an EPA Region 6 response on the federal PSD threshold and complete-project scope, and ask Gov. Greg Abbott to publicly urge TCEQ to withhold approval until the record is complete. These offices should publish their inquiries and the answers they receive.

Sen. Ted Cruz and Sen. John Cornyn

Request a congressional inquiry to EPA Region 6 on the 100-versus-250-tpy threshold, ORC scope, and federal Clean Air Act compliance.

Cruz 512-916-5834 · Cornyn 512-469-6034

Gov. Greg Abbott

Ask him to call publicly for no approval until the record is complete, a voluntary public meeting, and a defensible written eligibility determination.

Opinion line · 512-463-1782
If TCEQ signs an approval

Contact counsel immediately and preserve the signed action, letter, envelope, email, and every notice. A Motion to Overturn may be available, but the deadline is short—generally receipt by the Chief Clerk within 23 days after TCEQ mails notice of the signed action. Filing does not automatically stay approval; counsel should consider an express stay request.

Answering the central question

The public record still does not demonstrate a fully reconciled basis for approval under this expedited registration

The application does not reconcile itself; it does not reconcile with the wider government record; material descriptions remain publicly unreconciled; and the ORC, PSD-threshold, source-boundary, and enforceability questions remain unresolved in the released material.

Together, those findings justify a harder look before TCEQ acts: release the full record, correct the internal inconsistencies, issue a written source-wide PSD determination, settle the ORC and complete project scope, create an enforceable operating envelope, and—if the complete project does not qualify for the EGU Standard Permit—require the appropriate case-by-case authorization, with the project-specific public process not ordinarily provided for this registration.

Source documents

Read and verify the underlying record

Applicant statements are identified as applicant statements. Independent calculations are labeled as such. Tracking labels and diagnostic screens are not presented as agency determinations. Unknowns remain identified as unknowns. Status and participation figures were checked September 2, 2026.

Reporter-ready downloads

Download the supporting exhibit packs

These compilations collect the cited pages most relevant to this review. The exhibit pack includes a read-me index; the site-map compilation places the principal project depictions together for comparison.